Multi-criteria methods for ranking project activities
DOI:
https://doi.org/10.2298/YJOR140618012HKeywords:
Project Management (PM), Ranking Indexes (RI), Multi-Criteria Ranking Method(MCRM), Analytical Hierarchical Process (AHP), Data Envelopment Analysis (DEA)Abstract
This paper presents multi-criteria methods for ranking project activities according to several ranking indexes. The methods are based on the Analytical Hierarchical Process (AHP), on Data Envelopment Analysis (DEA), and on the use of common ranking indexes. This paper reviews ranking indexes of project activities for project management tasks. The ranking of project activities in one project is applicable for focusing the attention of the project manager on important activities. The selection of the appropriate ranking indexes should be done in accordance with managerial purposes: 1) Paying attention to activities throughout the execution phase and in the resources allocation process, in order meet pre-determined qualities, and to deliver the project on time and within budget, i.e., to accomplish the project within the "iron triangle" 2) Setting priorities in order to share the managerial care and control among the activities. The paper proposes to use multi-criteria ranking methods in order to rank the activities in a case where several ranking indexes are selected.References
Adler, N., Friedman, L. and Sinuany-Stern, Z., "Review of ranking methods in the DEA context", European Journal of Operational Research, 140 (2) (2002) 249–265.
Anderson, P., and Peterson, N.C., "A procedure for ranking efficient units in DEA", Management Science, 39 (10) (1993) 1261–1264.
Charnes, A., Cooper, W.W., and Rhodes, E., "Measuring the efficiency of decision making units", European Journal of Operational Research, 2 (6) (1978) 429–444.
Cho, J.G., and Yum, B.J., "An uncertainty importance measure of activities in PERT networks", International Journal of Production Research, 35 (10) (1997) 2737-2758.
Creemers, S., Demeulemeester, E. and Van de Vonder, S., "A new approach for quantitative risk analysis", Annals of Operations Research, 213 (1) (2014) 27-65.
Creemers, S., Demeulemeester, E. and Van de Vonder, S., "Project risk management: A new approach", IEEE International Conference on Industrial Engineering and Engineering Management (IEEM), 2011, 839-843.
Creemers, S., Demeulemeester, E., and Van de Vonder, S., "A new approach for quantitative risk analysis", Annals of Operations Research, 213 (1) (2014) 27-65.
Davis, E.W., and Patterson, J.H., "A comparison of heuristic and optimum solutions in resource-constrained project scheduling", Management Science, 21 (8) (1975) 944-955.
Demeulemeester, E., and Herroelen, W., International Series in Operations Research and Management Science: Vol. 49, Project scheduling—A Research Handbook, Boston, Kluwer Academic, 2002.
Demeulemeester, E., and Herroelen, W., "New benchmark results for the resource-constrained project scheduling problem", Management Science, 43 (1997) 1485–1492.
Edwards, W., "How to use multi attribute utility measurement for social decision making", IEEE Transactions on Systems, Man and Cybernetics, 7 (1977) 326-340.
Edwards, W., and Barron, F.A., "Smarts and SMARTER: Improved simple methods for multi attribute utility measurement", Organizational Behavior and Human Decision Processes, 60 (1994) 306-324.
Elmaghraby, S.E., "On criticality and sensitivity in activity networks", European Journal of Operational Research, 127 (2) (2000) 220-238.
Friedman, L. and Sinuany-Stern, Z., "Scaling units via the canonical correlation analysis in the DEA context", European Journal of Operational Research, 100 (3) (1997) 629-637.
Ganley, J.A., and Cubbin, S.A., Public Sector Efficiency Measurement: Applications of Data Envelopment Analysis. Elsevier Science Publishers, Amsterdam, North-Holland, 1992.
Goldrat, E., Critical Chain. The North River Press, Great Barrington, 1997.
Golenko–Ginzburg, D., "A two-level decision–making model for controlling stochastic projects", International Journal of Production Economics, 32 (1) (1993) 117–127.
Gray, C.F., and Larson, E.W., Project Management: The Management Process, third ed. McGraw-Hill, New York, 2005.
Hadad, Y., and Hanani, Z.M., "Combining the AHP and DEA methodologies for selecting the best alternative", International Journal of Logistics Systems and Management, 9 (3) (2011) 251-267.
Hadad, Y., and Keren, B., "Decision support model for ranking project network activities based on multiple criteria of precedence, duration, and cost", International Journal of Engineering Management and Economics, 4 (1) (2013) 1-17.
Helgeson, W.B., and Birnie, D.P., "Assembly line balancing using the ranked positional weight technique", Journal of Industrial Engineering, 12 (4) (1961) 394-398.
Kelley, J.E. Jr., and Walker, M.R., "Critical Path Planning and Scheduling", in: Proceedings of the Eastern Joint Computer Conference, Boston MA, 1959, 160–173.
Kelley, J.E. Jr., "Critical Path Planning and Scheduling: Mathematical Basis", Operations Research, 9 (1961) 296–320.
Keren, B., and Cohen, Y., "Optimizing project performance: the triangular trade-off optimization approach", International Journal of Engineering Management and Economics, 3 (2012) 152–170.
Khorramshahgol, R., and Steiner, H., "Resource analysis in project evaluation: A multicriteria approach", Journal of Operational Research Society, 39 (9) (1988) 795–803.
Khorramshahgol, R., and Vassilis, S., "Delphic Hierarchy Process (DHP): A methodology for priority setting derived from the Delphi Method and Analytical Hierarchy Process", European Journal of Operational Research, 37 (3) (1988) 347–354.
Khorramshahgol, R., "An integrated approach to project evaluation and selection", IEEE Transactions on Engineering Management, 35 (4) (1988) 265–271.
Kolisch, R., and Hartmann, S., "Experimental investigation of heuristics for resource constrained project scheduling - An update", European Journal of Operational Research, 174 (2006) 23–37.
Kolisch, R., and Padman, R., "An integrated survey of deterministic project scheduling", Omega, 29 (2001) 249–272.
Laslo, Z., "Project portfolio management: An integrated method for resource planning and scheduling to minimize planning/scheduling-dependent expenses", International Journal of Project Management, 28 (2010) 609–618.
Laslo, Z., and Gurevich G., "A simulation-based decision support system for managing information technology project portfolios", International Journal of Information Technology Project Management, 4 (2) (2013a) 1-17.
Laslo, Z., and Gurevich G., "PERT-type projects: time–cost tradeoffs under uncertainty", Simulation, 89 (3) (2013b) 278-293.
Levy, H., and Sarnat, M., Capital Investment and Financial Decisions. Prentice-Hall, Englewood Cliffs, New Jersey, 1995.
Mahmood, M.A., Pettingell, K.J., and Shaskevich, A.I., "Measuring productivity of software projects: A data envelopment analysis approach", Decision Sciences, 27 (1) (1996) 57–80.
Martin, J., "Distribution of the time through a directed acyclic network", Operations Research, 13 (1) (1965) 46–66.
Roy, B., "The outranking approach and the foundations of ELCTRE methods", in: C. A. Bana e Costa, (ed.), Readings in Multiple Criteria Decision Aid, Springer - Verlag, Berlin, 1989.
Roy, B., "Decision-aid and decision-making", European Journal of Operational Research, 45 (1990) 324-331.
Saaty, T.L., The Analytic Hierarchy Process, Planning Priority Setting Resource Allocation, McGraw-Hill, New York, 1980.
Sexton, T.R., Silkman, R.H., and Hogan, A.J., "Data envelopment analysis: Critique and extensions", in: R.H. Silkman, (ed.), Measuring Efficiency: An Assessment of Data Envelopment Analysis, Jossey-Bass, San Francisco, CA, 1986, 73-105.
The Project Management Institute, Guide to the project management body of knowledge (PMBOK guide), Newton Square: The Project Management Institute, 2008.
Van Slyke, R.M., "Monte Carlo methods and the PERT problem", Operations Research, 11 (5) (1963) 839-860.
Vanhoucke, M., "Using activity sensitivity and network topology information to monitor project time performance", Omega, 38 (5) (2010) 359-370.
Williams, T.M., "Criticality in stochastic networks", Journal of Operations Research Society, 43 (4) (1992) 353-357.
Yeo, K.T., "Project cost sensitivity and variability analysis", International Journal of Project Management, 9 (2) (1991) 111-116.
Downloads
Published
Issue
Section
License
Copyright (c) 2016 YUJOR
This work is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License.